Electrical Engineering · Question Bank
Electrical Power Plant
98 of 195 questions match · page 1 of 5. Answer in your head first, then check the solution.
#1📜 EE Pre-Board August 2012📘 PowerhouseEasy
The efficiency of thermal plant is approximately _.
#2📜 EE Pre-Board March 2013📘 PowerhouseEasy
The purposes of a grid system is to
AInterconnect the power stations
BSupply energy to remote areas
CMake extra high voltage available to consumers
DMake distribution of energy at reasonable cost
#3📜 EE Pre-Board March 2013📘 PowerhouseEasy
The efficiency of thermal plant is approximately
#4📜 EE Pre-Board March 2013📘 PowerhouseEasy
The useful life of diesel engine in a power plant is expected to be ______ year/s.
#5📜 EE Pre-Board August 2013📘 PowerhouseEasy
The efficiency of thermal power plant is approximately
#6📜 EE Pre-Board March 2014📘 PowerhouseEasy
The purpose of a grid system is to
Ainterconnect the power stations
Bsupply energy to remote areas
Cmake extra high voltage available to consumers
Dmake distribution of energy at reasonable cost
#7📜 EE Pre-Board August 2014📘 PowerhouseEasy
Which of the following plants will take least time in starting from cold conditions to full-load operation?
Agas turbine
BNuclear power plant
Csteam power plant
Dhydroelectric
#8📜 EE Pre-Board August 2014📘 PowerhouseEasy
Heating value of coal largely depends on
AAsh content
BMoisture content
CVolatile matter
DSize of coal particles
#9📜 EE Pre-Board August 2014📘 PowerhouseEasy
The efficiency of thermal plant is approximately
#10📜 EE Pre-Board March 2015📘 PowerhouseEasy
During load shedding
ASystem voltage is reduced
BSome loads are switched off
CSystem power factor is changed
DSystem frequency is reduced
#11📜 EE Pre-Board August 2015📘 PowerhouseEasy
Which plant can never have 100% load factor?
AHydro
BPeak load plant
CNuclear
DBase load plant
#12📜 EE Pre-Board March 2016📘 PowerhouseEasy
Converts energy of water to mechanical energy.
Apump
Bturbine
Cgenerator
Ddraft tube
#13📜 EE Pre-Board March 2017📘 PowerhouseEasy
Which of the following plants will take least time in starting from cold condition to full load operation?
Agas turbine
Bsteam power plant
Cnuclear power plant
Dhydroelectric power plant
#14📜 EE Pre-Board March 2017📘 PowerhouseEasy
When a power plant is not able to meet the demand of consumers it will resort to
Aload shedding
Befficiency plant operation
Cpower factor improvement at the generators
Dpenalizing high load consumers by increasing the charges of electricity
#15📜 EE Pre-Board March 2017📘 PowerhouseEasy
Which is the most reliable power plant?
#16📜 EE Pre-Board March 2018📘 PowerhouseEasy
Assuming the most efficient technologies for the extraction of energy, the fuel with the largest known reserves is
ACoal
BOil
CNatural gas
DNuclear
#17📜 EE Pre-Board March 2018📘 PowerhouseEasy
In a hydroelectric power plant, it is used to prevent the sudden rise and drop of water pressure.
APenstock
BIntake tower
CDam
DSurge tank
#18📜 EE Pre-Board March 2018📘 PowerhouseEasy
The process by which a heavy nucleus is splitted into two light nuclei is known as
ASplitting
BFission
CFusion
DDisintegration
#19📜 EE Pre-Board March 2018📘 PowerhouseEasy
Efficiency of a power plant is more in summers or winters?
Asummers
Bwinters
Csame in both
Ddepends on variation
#20📜 EE Pre-Board March 2018📘 PowerhouseEasy
The efficiency of thermal power plant is approximately
More Electrical Engineering topics