The useful life of diesel engine in a power plant is expected to be ______ year/s.
A5
B1
C50
D15
#22📜 EE Pre-Board March 2013📘 PowerhouseEasy
The average weekly energy generated by a thermal plant is \(7 \times 10^{6}\) kWhr. The peak load of the plant is 75,000 kW during the week. If the plant has an installed capacity of 100 MW, solve for the load factor of the plant.
A48.92%
B56.34%
C50.44%
D55.55%
#23📜 EE Pre-Board August 2013📘 PowerhouseEasy
The efficiency of thermal power plant is approximately
A10%
B30%
C60%
D80%
#24📜 EE Pre-Board March 2014📘 PowerhouseEasy
The purpose of a grid system is to
Ainterconnect the power stations
Bsupply energy to remote areas
Cmake extra high voltage available to consumers
Dmake distribution of energy at reasonable cost
#25📜 EE Pre-Board March 2014📘 PowerhouseEasy
An industrial plant has an aggregate load of 100 kW. The demand factor is 60%. The average total energy consumption of the plant in one year is 186 MWHR. What is the yearly load factor of the plant?
A32.45%
B42.25%
C38.67%
D35.39%
#26📜 EE Pre-Board August 2014📘 PowerhouseEasy
Which of the following plants will take least time in starting from cold conditions to full-load operation?
Agas turbine
BNuclear power plant
Csteam power plant
Dhydroelectric
#27📜 EE Pre-Board August 2014📘 PowerhouseEasy
Heating value of coal largely depends on
AAsh content
BMoisture content
CVolatile matter
DSize of coal particles
#28📜 EE Pre-Board August 2014📘 PowerhouseEasy
The efficiency of thermal plant is approximately
A10%
B30%
C60%
D80%
#29📜 EE Pre-Board August 2014📘 PowerhouseEasy
A power plant is said to have had a use factor of 48.5% and a capacity factor of a 42.4%. How many hours did it operate during the year?
A7,660
B8,660
C5,660
D6,660
#30📜 EE Pre-Board March 2015📘 PowerhouseEasy
In a certain country the energy consumption is expected to double in 10 years. Calculate the growth rate.
A4%
B3.96%
C13.86%
D6.93%
#31📜 EE Pre-Board March 2015📘 PowerhouseEasy
During load shedding
ASystem voltage is reduced
BSome loads are switched off
CSystem power factor is changed
DSystem frequency is reduced
#32📜 EE Pre-Board August 2015📘 PowerhouseEasy
Which plant can never have 100% load factor?
AHydro
BPeak load plant
CNuclear
DBase load plant
#33📜 EE Pre-Board August 2015📘 PowerhouseEasy
A power plant gets water from a dam from a height of 122.45 meters at the rate of 1,000 cubic meters per minute. If the output of the plant is 15,000kW, what is the plant efficiency?
A65%
B70%
C75%
D80%
#34📜 EE Pre-Board March 2016📘 PowerhouseEasy
Converts energy of water to mechanical energy.
Apump
Bturbine
Cgenerator
Ddraft tube
#35📜 EE Pre-Board March 2016📘 PowerhouseEasy
A diversity factor of 2 gives a saving of ___ % in generating equipment.
A33
B50
C67
D75
#36📜 EE Pre-Board March 2017📘 PowerhouseEasy
Which of the following plants will take least time in starting from cold condition to full load operation?
Agas turbine
Bsteam power plant
Cnuclear power plant
Dhydroelectric power plant
#37📜 EE Pre-Board March 2017📘 PowerhouseEasy
When a power plant is not able to meet the demand of consumers it will resort to
Aload shedding
Befficiency plant operation
Cpower factor improvement at the generators
Dpenalizing high load consumers by increasing the charges of electricity
#38📜 EE Pre-Board March 2017📘 PowerhouseEasy
The annual load curve is a straight line from 40 MW to 8 MW. What is the annual load factor?
A0.8
B0.7
C0.6
D0.9
#39📜 EE Pre-Board March 2017📘 PowerhouseEasy
Which is the most reliable power plant?
ASteam
BHydro
CWind
DTidal
#40📜 EE Pre-Board March 2017📘 PowerhouseEasy
A 75 MW power plant has an average load of 35,000 KW and a load factor of 65%. Find the reserve over peak.